Sidewalk Program

Map of Sidewalk Repair Districts

2019 Sidewalk Repair and Infill Program

As of the end of 2017, all 7 Districts in Waverly have been inspected for damaged sidewalk.  As soon as the frost is out of the ground, the City will again begin inspections.  If you own property within District 2, after the inspections have been completed, you will be notified by letter if your sidewalk requires repair and the options available to you. 

Also, the City will now identify locations in District 2 where there are gaps in the sidewalk system.  Property owners adjacent to these gapped sidewalks may now be asked to complete these sections so the neighborhood is more pedestrian friendly.

2018 Sidewalk Repair Program Schedule

Invoices have been finalized and were mailed out on December 18, 2018.  These invoices are due January 11, 2019.  Please contact Public Works Administration at 352-9065, if you were expecting an invoice and have not received one yet.

2019 Sidewalk Repair Program Schedule

March/April...  City inspects sidewalks for needed repairs.
May................Property owners are mailed notification if their sidewalk needs to be repaired.
May - Aug......Property owners can repair their own sidewalk or hire a contractor to complete the work.  A sidewalk permit is required.  Work must be completed by August 30th.
Sept...............City's hired contractor repairs all sidewalk that has not been completed by the property owner.  Improvements will be invoiced or assessed accordingly.
Oct/Nov........ Invoices finalized and mailed out.


Standard Sidewalk Inspection Guidelines

Photo of typical corner Ped. Ramp

A high quality of life, friendly and progressive merchants, and a college town atmosphere; this is Waverly, Iowa.